Project Overview
MDE is undertaking the electrical installation works for the Buncrana Schools – Scoil Iosagain project. This phased educational development involves the construction of a new primary and special needs school, extensive site works, and the demolition of existing school buildings. The project will be executed in three sequential phases to ensure minimal disruption to school operations.
The new school will be built on the existing site of the Sacred Heart building, west of St. Patrick’s Road. The first phase involves constructing the initial section of the new school behind the Sacred Heart building, which will remain operational during this phase. Once completed, the school will relocate to this section, allowing for the demolition of Sacred Heart and the construction of the second section. Following this, St. Columba’s will be demolished in the final phase, and the site will be redeveloped to include parking, three hard ball courts, and improved access routes.
The overall project duration is expected to be 27 months, divided into:
- Phase 1 (13 months): New build construction
- Phase 2 (12 months): Demolition of Sacred Heart and completion of the second section of the school
- Phase 3 (2 months): Demolition of St. Columba’s and final site works
Scope of Works
MDE’s scope of work for the Buncrana Schools project includes the supply, installation, and commissioning of the following electrical services:
- Site Lighting – Installation of external and internal lighting systems.
- Site Power – Provision of electrical power distribution throughout the site.
- Site Mechanical Services – Electrical support for mechanical systems.
- Main Switch Board & Sub-Distribution Board – Installation of power distribution systems.
- Sub Mains Cabling – Implementation of mains and sub-main power cabling.
- Electrical Containment – Cable containment and management systems.
- Small Power Installation – General electrical outlets and power distribution.
- Controls Installation – Integration of electrical control systems.
- Lift Electrical Services – Electrical provisions for lift operations.
- Lighting & Emergency Lighting Installation – Complete internal and external lighting solutions, including emergency lighting.
- Structured Cabling – Implementation of IT network infrastructure.
- Television Installation – Provision for TV and media systems.
- Deaf Loop Installation – Installation of hearing support systems.
- Interactive Whiteboard Installation – Setup of smart learning technology.
- Fire Alarm Installation – Design and installation of fire detection and alarm systems.
- Wheelchair Refuge Installation – Emergency communication points for accessibility.
- Lightning Protection Installation – Ensuring building protection from electrical surges.
- Mag-Lock & Intercom Installation – Secure access control systems.
- Intruder Alarm & CCTV Installation – Security system implementation for enhanced safety.
- Earth Bonding & Testing – Grounding and electrical safety testing.
- Testing & Commissioning of Electrical Services – Ensuring full system functionality before handover.
- Builders Work, Coordination & As-Installed Drawings – Providing accurate documentation and coordination with other contractors.
- Operation & Maintenance Documentation – Full documentation for long-term management and maintenance.
- Training & Handover – Demonstration and training for school personnel on the new electrical systems.
- Defects Liability Period Support – Addressing any post-completion obligations.
Key Project Features
- Phased Construction: The project will be executed in three phases to minimize disruption to school activities.
- Modern Learning Facilities: The development will provide state-of-the-art classrooms, special needs facilities, and recreational areas.
- Sustainability & Safety: Advanced electrical systems and infrastructure will enhance energy efficiency and security across the site.
- Improved Site Accessibility: The redevelopment will introduce better traffic management, including new parking and access routes.
Project Timeline
The project is expected to span 27 months, with phased handovers ensuring that educational activities continue uninterrupted. MDE is committed to delivering high-quality electrical installations that meet the project’s efficiency, safety, and sustainability requirements.
Project Impact
The Buncrana Schools – Scoil Iosagain project is a significant investment in the local education sector, providing modern learning environments and enhanced facilities for students and staff. MDE is proud to be part of this transformative initiative, ensuring a future-ready school equipped with advanced electrical infrastructure.