Lidl Tallaght, Dublin 24

Key Information

Location Dublin 24

Client Lidl Ireland GmbH

Consultant Noel Lawler

Overall Project Value €6 million

About This Project

Our fast track fit out of Lidl in Tallaght incorporated new design concepts including new mechanical, electrical, and ventilation and installation services.

This challenging project took 12 weeks to complete all within a busy functioning store, demonstrating the ability of our management and site personnel to complete such a project on time and within budget.

Given our track record and experience, we were able to continue work without disruption to the Lidl store, its staff, customers, or service.

MDE Installations specialise in installations and fit out in live working environments and have built up considerable expertise that we can offer to clients in keeping a site operational through careful project management and control. This includes the highest level of health and safety requirements.

Project Challenges at a Glance

  • Coordinating various services with other third parties.
  • Live and busy site adjacent to Lidl’s headquarters.
  • Maintaining and exceeding a high level of health and safety.
  • Managing and maintaining site operatives on shiftwork basis.
  • Completing project defect/snag free.